Waterside Campus

NORTHAMPTON

The £330 million Waterside Campus comprises a Creative Hub, a Learning Hub, a Sports Pavilion, a Senate Building and a Logistics Hub.

  • SCOPE OF WORK

    Waterside Campus

    • Design and installation of post-tensioned slab solution for Creative Hub and Learning Hub.
    • Adaptation of installation technique to achieve uniform aesthetic across fair-faced soffits.
    • Coordination of post-tensioning tendon layout around embedded radiant cooling pipes within the slab.
    • Coordination of post-tensioning anchorages to suit mullion fixing locations for the cladding system.
  •  
  • GALLERY

    Waterside Campus

  • Image Thumbnail
    Image Thumbnail
  • Image Thumbnail
  • Image Thumbnail

BENEFITS

CCL delivered the following benefits:

  • vertical_align_bottom

    Material Reduction

    Reduced slab thickness of levels 1-4 in the Creative Hub by 50 mm. Reduced slab thickness of levels 1-5 in the Learning Hub by 75 mm.

  • layers

    Flawless Aesthetic

    Achieved the architect’s vision with featured exposed soffits and minimal slab seams.

  • line_weight

    Weight Reduction

    A reduction in concrete of almost 2000 m³ across both buildings

  • check

    Cost Savings

    Less concrete resulted in faster construction and significant savings.

  • flip_to_front

    Design Flexibility

    Our design accommodated embedded radiant cooling networks.

  • open_with

    Increased Floorspace

    Longer spans and fewer vertical supports allowed for an uninterrupted performance arts space within the Creative Hub.