SUNY

PLATTSBURGH, USA

The State University of New York, Plattsburgh is part of the largest state-supported comprehensive university system in the US.

  • SCOPE OF WORK

    SUNY

    • Design of corrosion prevention system for podium slab and pedestrian bridge when corrosion was discovered within these structures.
    • Location of existing reinforcement using GPR.
    • Preparation of 3,600 cavities to accept cathodic protection anodes.
    • Chasing out of 2,134 m of channels to accept the connecting wires.
    • Installation of impressed current cathodic protection system.
    • Testing of each zone prior to encapsulation.
    • Grouting of voids.
    • Placement of titanium mesh before casting of 15 cm concrete topping slab.
  •  
  • GALLERY

    SUNY

  • Image Thumbnail
    Image Thumbnail
  • Image Thumbnail
  • Image Thumbnail

BENEFITS

CCL delivered the following benefits:

  • security

    Structural Integrity

    Installation of cathodic protection halted corrosion.

  • check

    Peace of Mind

    Meticulous preparation ensured no costly modifications once system installed.

  • view_quilt

    Minimal Structural Disruption

    Precise location of cavities avoided existing reinforcement and maintained structural integrity.

  • trending_down

    Reduced Ongoing Maintenance Costs

    Training of university maintenance personnel allowed system monitoring to be carried out in-house.